The construction of the section of the North-East of the chord from Dmitrovsky to the Yaroslavl highway is planned to finish by 2022. About during the inspection of works said the mayor of Moscow Sergey Sobyanin, the Agency "Moscow".

"This section from Dmitrovka to Yaroslavl – the most difficult, the most intense engineering structures, 10 bridges and overpasses, including one of the largest trestles – 2.4 kilometres. For Moscow, in a complex confined environment, when close to houses, construction sites, railway, communication is a complex project. But, as I understand it, builders do their task has been active on this site, and today a quarter of the amounts disbursed", – said the mayor. According to Sergei Sobyanin, the site will improve transport accessibility of 800 thousand inhabitants of the North-East of the capital.

Project Manager at PJSC "s" Valery Faber said that this area holds more than 20% of the work. "Trestles are being constructed in full swing. Also started the installation of new bridges across the Yauza river, over the river Likhoborka river," he says.

The Deputy mayor of the city for urban policy and the construction of Andrey Bochkarev stressed to run traffic on this section of TSW will gradually on a separate road elements.

This highway will be without traffic lights with three lanes in each direction. In the area of the chord will have three overpasses.

In total, the project will be built and reconstructed 22.6 km of roads.

Before the second overpass will be built between terminals. It is emphasized that after the first stage of construction will be possible, the movement of trains-Shuttle from South terminal complex to the North.